Newest Model Bear Den

Bear Den Log Home Design

The Bear Den is our newest model and is currently in the process of being built.  Stay tuned here or follow us on Facebook, #CLCBearDen to see progress photos and updates!

Build Days 81-91

Finishing touches and punchlist items.  Appliances placed and final inspections and occupancy permit.

Build Days 79-81

Staircase installed

Build Days 73-78

Wall, ceiling boards and trim completed.  First floor flooring started.

Build Days 71 - 72

Kitchen cabinet installation

Build Days 69 - 70

Furnace installation and testing

Build Days 63 - 68

Septic installed

Build Days 58 - 62

Deck boards laid and deck structures finished.

Build Days 56 - 57

Deck piers installed

Build Days 53 - 55

  • Finishing insulation in kitchen ceiling, and ceiling boards to prep kitchen for poly and flooring.
  • Installing ship lap on first floor.
  • Staining and applying poly to interior trim and doors.
  • Back filling is done and deck and porch posts are in.
  • Septic field is being excavated.

Build Days 51 - 52

Propane tank installation.

Build Days 31 - 50

Floor, wall and ceiling insulation started.

Build Days 29 - 30

Well drilled, installed, and hooked-up.  Water is running.

Build Days 18-28

HVAC/Plumbing/Electrical continued.

Build Days 12-17

HVAC/Plumbing/Electrical rough in started.

Build Days 9-11

Interior walls are completed and windows installed.  Trusses are all placed and roof has been installed.

Build Day 8

Main cabin trusses are set.  Left gable wall logs are almost complete.

Build Day 7

Main log wall stacking complete and ready for gable logs and scissor trusses.  Trusses to be delivered and set next morning.

Build Day 6

All Advantech subfloor on the second story is complete.  Stacking of the second story logs has started.

Build Day 5

All floor trusses have been set.  Bedroom side ledger boards have been installed and first 2 rows of Advantech subfloor have been installed.

Build Day 4

Exterior staining of the first floor is complete.  Load bearing studwall has been installed and floor trusses have started to be installed.

Build Day 3

Two more deliveries of materials are received onsite.  The floor trusses for the 2nd floor and mechanical openings are also delivered.  Staining was started on the first floor.

Build Day 2

The first floor wall system is completed.

Build Day 1

May 6th, 2019 is the first official build day!

Flooring was completed and the log wall system started going up!

Pier Foundation

As of May 3rd,  2019 all of the following have been completed:

  • Pier foundation placed and concreted

Driveway & Excavation

As of April 15th,  2019 all of the following have been completed:

  • Permits received
  • Driveway excavated and stoned
  • Cabin foundation excavation

Driveway & Cabin Placement

Design

Lot Preparation

As of January 15th,  2019 all of the following have been completed for lot preparation:

  • Design drawings finalized
  • Land purchased
  • Sewer survey
  • Rough stakeout of Bear Den
  • Driveway Stakeout
  • Application for sewer permit submitted
  • Application for driveway permit submitted
  • Tree removal lot clearing
  • Cutting in of driveway
  • Plot plan
  • Applied for zoning